Retail auto parts company opening 320 stores per year.
|
|
Challenge
|
Improve on-time completion (Stores are 5,000-14,000 sq ft each)
|
|
Solution
|
|
Work with management to:
|
| * |
Set long term framing package pricing. |
| * |
Set up flexible shipping arrangements. |
| * |
Adopt standard sets of plans. |
| * |
Dip apply top coat paint at the joist plant. |
| * |
Identify, cost, and eliminate job site practices that slow down the project schedule. |
|
|
Result
|
A smoother job with fewer on-site bottlenecks,
lower total job costs, and a schedule that works. |
|