Fast-growing grocery company opening 65 stores per year.
|
|
Challenge
|
Improve completion time of six store openings per month; Stores are 35,000-100,000 sq ft.
|
|
Solution
|
|
Team up with the owner, general contractor, and steel supplier to achieve their goal by:
|
| * |
Setting standard bay framing. |
| * |
Setting up multiple plant shipping arrangements. |
| * |
Adopt standard sets of plans. |
| * |
Setting up direct contact with architect; developing streamlined approval process. |
| * |
Identifying, costing, and eliminating job site practices that slow down the project schedule. |
|
|
Result
|
All items were directly negotiated. The result is a smoother job, lower total job costs, and a schedule that works.
|
|